Regulated environments, compressed timelines, zero margin for error.
KIRCO MANIX recently completed the Prototype Line at ONE Circle Gigafactory for Our Next Energy (ONE), a Michigan-based battery technology company. The 659,000 SF facility is one of the largest lithium iron phosphate battery factories in the United States, focused on cell and battery manufacturing, raw material refinement, and cathode materials production.
Cells produced are fully IRA compliant, requiring careful attention to compliance standards throughout construction to ensure safe and sustainable battery chemistries for EVs and stationary storage solutions.
Retrofitting an existing 659,000 SF precast building into a highly regulated EV battery factory presented unique challenges, as the space was never designed for this purpose. KIRCO MANIX navigated tight structural constraints, strict humidity controls, and a client-requested timeline reduction from 32 to 24 weeks, managing a 7-day work week and careful labor scheduling to deliver on time and on budget.